Shortage of gas, faults and maintenance
works on plants have combined to reduce power generation in the country
to 3,674.9 megawatts from the 6,668.6MW available capacity of the power
stations as of Monday.
Available generation records from the
National Control Centre and the Transmission Company of Nigeria showed
that 2,993.7MW was the quantum of electricity that the system was losing
due largely to gas shortage.
Since the handover of the Power Holding
Company of Nigeria successor companies to new investors, the generation
firms have been complaining of a drop in the supply of gas to fire
their plants.
The development has led to erratic
electricity supply across the country although there have been promises
of improvements in the near future.
About 80 per cent of the power plants,
which are gas-fired, are deprived of regular gas supply. The Geregu,
Omotosho and Olorunsogo plants with available capacities of 414MW, 126MW
and 252MW could only generate 143MW, 81.2MW and 164.7MW, respectively
due to gas constraints.
As of 6am on Monday, January 27, 2014,
the Geregu and Omotosho National Integrated Power Project plants had
available capacities of 435MW and 500MW but were only able to generate
60MW and 102.5MW, respectively due to low gas pressure.
The Sapele NIPP, with 250MW available
capacity, was totally out due to gas constraints, loading problem and
civil work on its basement.
The National Control Centre, Osogbo,
Osun State, said the 500MW Olorunsogo NIPP plant was also out due to gas
constraints and maintenance after a commissioning test.
The Alaoji plant has also been shut down
following a water injection test, while the Egbin Power Station, with
880MW available capacity, was on Monday generating 703MW.
The NCC said generation at the nation’s
largest power plant was limited by the inability of the Nigerian Gas
Company to supply enough gas to it.
It said that Egbin’s installed available
capacity was reduced because of an ongoing high turbine rotor vibration
rehabilitation work.
Also, the Sapele, Delta and Afam IV-V
power plants, which on Monday had 120MW, 375MW and 75MW available
capacities, could only generate 68MW, 346MW and 50MW, respectively due
to low lube oil pressure, faults and maintenance works.
The Kainji Hydro Plant was totally out
due to rehabilitation. The NCC said the rehabilitation of its 1G5 unit
was ongoing as of Monday, while the 1G6 unit was already out for
rehabilitation since December 6, 2013 and is expected back on December
31, 2014. The 1G7 unit was out on stator winding E/F, while the 1G8
unit was out on fault.
The 1G9 unit at the Kainji plant was
also out due to upper guide bearing temperature problem, while the 1G10
unit was said to be out due to thrust bearing temperature but available
for station service.
The 1G11 unit of the plant was shut down
on emergency due to abnormal noise in the unit, while the 1G12 unit was
out for rehabilitation.
The Shiroro Hydro Plant was said to have
an installed available capacity of 450MW as of 6am on Monday but could
only generate 300MW due to ongoing repairs and overhaul.
However, the power plant was shut for three days on Monday, and the problem is expected to last till Wednesday.
The General Manager, Public Affairs,
TCN, Mrs. Seun Olagunju, said in a statement on Sunday that the shutdown
of the station was to enable the engineering maintenance crew to
rectify a ground fault on the station’s carbon dioxide control panel.
The panel, according to Olagunju, provides vital auxiliary services necessary for the running of the Shiroro plant.
She explained that the control panel was
a fire protection system for all the units in the power station and
that if it was out on repairs, all the units would have no protection
against fire outbreak, hence the need to shut all of them.
The statement read in part, “During the
period, grid generation will reduce by 300MW, hence the nationwide load
shedding. The impact of the load shedding will be higher in the northern
part of the nation, especially Kano, due to voltage instability issues
previously affecting power supply in that area.”
Similarly, the Jebba Hydro Plant had 385.6MW but was only able to do 327MW due to ongoing maintenance.
The Managing Director, Korea Electric
Power Nigeria Limited, the technical partner and managers of the Egbin
Power Station, Mr. Gyoo Chull Yeom, who recently underscored the dire
gas supply situation to the power plants, said, “Gas is not coming, and
without this, the power plants cannot operate optimally. Gas supply is
very important to the Nigerian power sector because almost 80 per cent
of the power plants in the country are gas-fired.
“Inadequate gas supply is a big problem
for Nigeria. Even with the private sector investment; if there is no
enough gas supply, there will still be problems.”
No comments:
Post a Comment